2011
| 12.29 |
Approve the altered execution plan(1st, 2nd district), Assign the altered district |
9.22
| Establish the altered development plan(1st, 2nd district) |
9.21
| Start construction of 5th apartment complex |
9.21
| Start construction of 14th and 15th apartment complex |
9.21
| Start construction of 1st~4th, 6th and 7th apartment complex |
2010
| 9.3 |
Approve the altered execution plan |
2.11
| assign the altered district, Establish the altered development plan |
2.01
| Start construction of 2nd complex |
2009
| 9.3 |
Start construction or 1st complex |
7.16
| Announce the design competition for the apartment in Magok district |
2008
| 12.3 |
Approve the execution plan |
2007
| 12.28 |
Assign the district and establish the development plan(Seoul City) |
12.26
| Approve the district assign(ministry of construction & Transportation) |
12.24
| Decide the broad area traffic improvement plan(Ministry of Construction & Transportation) |
4.04
| Review the seoul urban plan committee |
1.22
| Hold the public hearing |
2006
| 12.29 |
Announce the exhibit for the assign the district |
1.04
| Announce the Magok R&D City (MRC) create district building approval limit |
2005
| 12.28 |
Report to the Magok District development support special committee(1st) |
12.2
| Announce the Magok R&D City (MRC) basic concept |